What your contractor won't tell you — but should.

Practical construction advice for private clients undertaking high-value residential projects across Solihull, Sutton Coldfield and the West Midlands.

Read the Articles
Latest Articles

Insights & Advice

Written from 20 years on construction projects — not from a marketing brief. Each article answers a question real clients ask before they appoint anyone.

Project Management · Luxury Extensions

Do I need a project manager for my home extension?

Most clients I speak to have never used a construction project manager before. They assume it's only for commercial builds, or that their architect will handle it, or that the main contractor will simply get on with it. None of those assumptions tend to hold up — especially once the project is live and problems start stacking.

Richard Bridgman · 8 min read ·
Read Article ↓
Cost Planning · Solihull · Sutton Coldfield

How much does a luxury home extension cost in 2026?

The question every client asks — and the one most contractors dance around. Here's what actually drives cost, and what a realistic budget looks like right now.

Richard Bridgman·7 min read·
Read Article ↓
Contractor Selection · West Midlands

How to choose a building contractor in the West Midlands

Finding a builder in Sutton Coldfield or Solihull isn't the hard part. Finding one that's right for a high-value project — solvent, experienced, and properly insured — is considerably harder.

Richard Bridgman·6 min read·
Read Article ↓
Building Contracts · Homeowner Advice

What should a building contract include?

Most homeowners sign a contractor's own terms without a second look. Some don't sign anything at all. Both are mistakes. Here's what a robust contract actually needs.

Richard Bridgman·9 min read
Coming Soon →
Planning Permission · West Midlands

Planning permission for a rear extension — what you actually need to know

Permitted development rights sound simple until your project sits in a Conservation Area, backs onto a neighbour who objects, or falls within Green Belt. I've navigated all three.

Richard Bridgman·7 min read
Coming Soon →
Due Diligence · Builder Vetting

Red flags to watch for when getting builder quotes

The quote that comes in significantly lower than the others is not a bargain. It's either priced incorrectly or it's missing scope that will reappear as variations on site.

Richard Bridgman·5 min read
Coming Soon →

Featured Article

Do I need a project manager for my home extension?

Richard Bridgman · · 8 min read · Project Management

Most people asking this question have already started to feel uneasy.

They've got planning permission. They've had a few contractor quotes back. And something isn't adding up — either the numbers are all over the place, or the architect has gone quiet, or the builder they liked the look of can't start for nine months. So they search online and end up here.

The honest answer is: probably yes. But let me explain why, because it's not the answer you might expect.

What a project manager actually does

There's a lot of confusion about this role — partly because the title gets used loosely, and partly because every professional on a construction project claims to be managing something.

Your architect manages the design. Your structural engineer manages calculations. Your contractor manages the build programme. None of them are managing the project on your behalf. That's a meaningful distinction.

A construction project manager working client-side — which is the only kind worth having on a residential project — works exclusively for you. Not for the contractor, not for the design team, not for anyone with a commercial interest in how the project is procured or priced. Their job is to make sure the right decisions get made at the right time, that your money is spent properly, and that when something goes wrong — and something always does — there's someone in your corner who knows what to do about it.

The assumption that costs people the most

The most expensive assumption I see is this: "the contractor will just get on with it."

They will get on with it. That's not the problem. The problem is that what they get on with — and what you thought you were getting — aren't always the same thing. Scope gaps, undefined finishes, unclear responsibilities between trades, a programme that was always optimistic — these things surface on site, under time pressure, when the cost of fixing them is highest.

"I've walked onto projects where a homeowner had spent six figures before realising their contract had no mechanism to control variations. No baseline. No agreed schedule of works. Just a price and a handshake. When the contractor came back with additional costs — and they always do — there was nothing to push back against."

That's not a contractor horror story. That's just what happens when no one sets the project up properly at the start.

When you probably don't need one

I'd rather be straight with you than sell you something you don't need.

If you're doing a relatively straightforward project — a single-storey rear extension, a loft conversion, something under £150,000 — and you have a recommended contractor you trust, a clear scope, and an architect who's going to be involved through to completion, you may manage fine without a dedicated project manager. You'll need to be hands-on, ask the right questions, and read your contract carefully. But it's achievable.

When you definitely do

The calculation changes as projects get more complex — and complexity isn't just about size. You likely need client-side representation if:

In these situations, the cost of proper representation — typically a percentage of the contract value — is almost always recovered in the savings made on variations, the problems caught before they become expensive, and the contractor relationships managed professionally rather than adversarially.

What it actually looks like in practice

On a typical high-value residential project in Solihull or Sutton Coldfield, I'd be involved from the pre-construction phase — before a contractor is even appointed. That means reviewing the design for buildability, pressure-testing the cost plan, helping select and tender to the right contractors, and making sure the contract is set up to protect the client rather than the builder.

Once on site, I'm the client's point of contact for anything that requires a decision — not every email, not every minor query, but the things that matter. Programme delays, variation requests, disputes between trades, quality concerns. The things that, if left unmanaged, compound.

Most clients tell me the same thing at the end of a project: they couldn't have done it without the support, and they wished they'd brought someone in sooner.

A straightforward way to think about it

If the money at stake would feel significant to lose, and you don't have a construction background — you need representation.

Not because contractors are dishonest. Most aren't. But because construction is a specialist environment, and the gap between what a client thinks they're buying and what they actually get is wide enough to drive a lot of expensive problems through.

Getting that right is exactly what I do.

If you're at the early stages of a project and want a conversation — no obligation, no sales pitch — get in touch directly.

Request a Private Consultation

Already have quotes back? The Pre-Contract Review is a fixed-fee, one-off alternative — £1,250, five working days, and credited in full against your first month if you go on to appoint.


Latest Article

How much does a luxury home extension cost in 2026?

Richard Bridgman · · 7 min read · Cost Planning

This is the question I get asked before almost any other, usually within the first five minutes of a first conversation. It's also the question I'm least able to answer honestly in one sentence — because the honest answer depends on decisions the client usually hasn't made yet.

That doesn't stop people wanting a number. So here is one, followed by everything that number depends on.

The number

For a high-specification residential extension in Solihull or Sutton Coldfield in 2026, budget somewhere between £2,500 and £4,500+ per square metre, depending on specification, site conditions and current market pricing. For a 50m² extension — a fairly typical size for a large kitchen-diner or family space — that puts a realistic build cost between £125,000 and £225,000, before professional fees, planning costs and VAT.

That range is wide on purpose. The gap between the bottom and the top of it is almost entirely down to decisions the client controls.

What actually drives the number

Four things move the price more than anything else:

Where the number people quote you goes wrong

Almost every over-budget project I've been brought in to rescue started with the same mistake: a figure was fixed in the client's mind before the design, the specification, or the site conditions were properly understood — usually from a number a friend mentioned, or something read online.

"A neighbour's extension from eighteen months ago tells you almost nothing about your own. Different footprint, different finish, different ground conditions, different point in the market. The only number worth trusting is one built from your actual drawings."

The second most common mistake is forgetting what sits outside the build cost entirely: planning application fees, building control, structural engineer and architect fees (typically 10–15% of build cost combined), VAT, and furniture, fixtures and equipment. On a £150,000 build, that can easily add another £25,000–£35,000 before the project is genuinely finished.

The contingency question

Every residential project should carry a contingency — and on anything involving structural work, existing building fabric, or a site you can't fully survey until walls come off, I'd budget 10–15% of build cost, not the 5% many quotes assume. This isn't pessimism. Older properties in particular tend to reveal at least one thing during the build that wasn't visible beforehand, and the cost of dealing with it needs to come from somewhere that isn't a panicked renegotiation of your kitchen budget.

A more useful way to approach it

Rather than starting with a fixed number and working backwards to a design that fits it — which usually ends in disappointment or a specification compromise nobody's happy with — it's worth starting with a proper cost plan built from your actual drawings, before you go anywhere near a contractor for pricing. That's the entire purpose of Pre-Construction Advisory: get the number right when it's still cheap to change your mind, not once you're three variations into a build.

A quote from a single builder is not a cost plan. It's one person's interpretation of a drawing, priced to win the job.

If you're at the budgeting stage and want a realistic number for your specific project — not a rule of thumb — get in touch directly.

Request a Private Consultation

Already got a quote back? The Pre-Contract Review checks it against current market rates before you sign — £1,250 fixed fee, five working days.


Article

How to choose a building contractor in the West Midlands

Richard Bridgman · · 6 min read · Contractor Selection

Finding a builder isn't difficult. The West Midlands has no shortage of contractors willing to price residential work. Finding the right one — for your project, at your budget, with the capacity and competence to deliver it properly — is a different matter entirely.

Most private clients approach contractor selection the same way: ask a couple of people for recommendations, get three quotes, pick the one in the middle. It's understandable. It's also one of the most reliable routes to a difficult project.

Why the quote tells you less than you think

A contractor quote is not a neutral document. It's a sales document, priced to win work. The figure at the bottom reflects how that contractor has interpreted the drawings, what they've chosen to include, and what margin they need at this point in their order book.

Two quotes for the same project can legitimately differ by 20–30% — not because one contractor is overcharging, but because they've priced different things. The lower quote may carry significant scope gaps that will resurface as variations once work is underway. The higher quote may be more comprehensive, or may simply reflect a contractor whose diary is full and who isn't particularly hungry for the work.

Comparing quotes at face value, without understanding what each one actually includes, is not due diligence. It's guesswork with a spreadsheet.

Financial standing matters more than most people check

A contractor's financial health is one of the most important things to verify before appointing them on any project above a certain value — and one of the things most homeowners never look at.

Contractor insolvencies are not rare events. They happen throughout the construction cycle, to businesses that looked entirely capable from the outside. When they happen mid-project, the client is typically left with a partially completed build, money already paid out, and a legal position that takes months and significant cost to resolve.

"I've seen a family lose eighteen months and over £80,000 to a contractor insolvency that basic due diligence would have flagged before a contract was signed. The warning signs were there in the accounts. Nobody looked."

Basic financial checks — Companies House filings, credit agency data, whether accounts have been filed on time and what they show — take under an hour. They're not infallible, but they filter out a category of risk that costs some clients everything.

Insurance and accreditation: the floor, not the ceiling

Any contractor working on a project of meaningful value should carry current public liability insurance (minimum £2 million for residential work, £5 million for anything larger or more complex) and employer's liability insurance. They should be able to provide certificates on request, without hesitation. If they can't, or won't, that tells you something important.

Scheme accreditations — FMB, CHAS, NHBC, Trustmark — provide a baseline level of comfort. They indicate that a contractor has met some minimum criteria and that there's a complaints process if things go wrong. They are not, however, a guarantee of quality or delivery competence. I've seen excellent contractors with no accreditations and very poor ones with several.

Treat accreditation as one input, not as a decision in itself.

References: how to use them properly

Every contractor can provide a reference. What matters is whether that reference is from a comparable project — similar value, similar complexity, similar specification — and whether the person giving it is real and reachable.

The question most people ask a reference is: "Would you use them again?" It's too broad to be useful. More telling questions are: how did they handle variations, were there any cost increases and how were they communicated, how did they respond when something went wrong, was the final account close to the original contract sum?

The answers to those questions tell you far more about how a contractor behaves under pressure than a general endorsement does.

Capacity and programme: a question most clients don't ask

A contractor's current workload directly affects how they'll perform on your project. A builder running three large projects simultaneously with a small team is not the same as one who has the capacity to genuinely focus on yours. This is worth exploring in conversation — not in a confrontational way, but directly. What else are they currently running? Who will be on site day to day? Is the person you're meeting actually involved in delivery, or does the project get handed to someone else once contracts are signed?

The answers matter. On a high-value residential project, continuity of key personnel — the site manager, the foreman — is one of the most significant factors in whether the project runs well or not.

The right question to ask yourself

After you've met with contractors, reviewed their quotes, checked their references and had a look at their financial standing, the most honest question to ask yourself is this: do I have enough information to make a genuinely informed decision here?

If the answer is no — if the quotes are inconsistent, the reference checks have raised questions, or you simply don't have the construction background to evaluate what you've been told — that's a reasonable time to bring in independent advice. Not because anything is necessarily wrong, but because the cost of getting this decision wrong is high enough to warrant getting it right.

Contractor selection is one of the most consequential decisions in any residential project. The right contractor, properly appointed under a robust contract, makes almost everything easier. The wrong one makes almost everything harder — and expensive.

If you're at the stage of selecting a contractor and want independent input on who to shortlist, how to run the tender, or how to review quotes before you commit — that's exactly the kind of work I do.

Request a Private Consultation

Already have quotes in hand? The Pre-Contract Review gives you an independent assessment of what you've been sent before you sign — £1,250 fixed fee, five working days.


Free Download — Homeowner's Guide

Before you appoint a contractor, read this first.

Five decisions that determine whether your high-value residential project runs smoothly — or unravels. Written for homeowners in Solihull and Sutton Coldfield undertaking extensions, renovations and new builds above £150,000.

  • How to structure a pre-construction phase properly
  • What your contract must include before work starts
  • The five most common budget failures — and how to avoid them
  • How to run a contractor tender that protects your position
  • What to do when a contractor requests a variation
Download Free Guide (PDF) Book a Consultation

No email required · Instant download